CUP: E13D13001700002
POTENZIAMENTO E COMPLETAMENTO DEL PERCORSO CICLOPEDONALE DI VIA G. CARDUCCI
SUMMARY OF THE PROJECT
IN LINEA CON GLI OBIETTIVI DELL'ASSE TEMATICO E, FSC 2014-2020, GLI INTERVENTI PREVEDONO IL MIGLIORAMENTO DELLA FRUIBILITÃ DEL SISTEMA DEI SERVIZI, DEGLI SPAZI PUBBLICI, AREE DI AGGREGAZIONE E VERDE PUBBLICO, L'INCREMENTO DELLA VIABILITÃ PEDONALE E CICLOPEDONALE, LA RIDUZIONE DELLE BARRIERE ARCHITETTONICHE ED ALTRO PER FAVORIRE L'ACCESSIBILITÃ DA E PER I NODI URBANI.
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 180,242.17 num
- Achieved
- 88,439.12 num
Funding monitored
€ 180,242.17
of which cohesion funds
€ 180,242.17
Given name | Amount |
---|---|
Development and Cohesion Fund | 180242.17 |
Payments monitored
€ 88,439.12
of which cohesion funds
€ 88,439.12
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 954.00 | 954.00 | 0 |
2023 | 87485.12 | 88439.12 | 49 |
State of progress
Open
Expected start: 14/07/2022
Effective start: 14/07/2022
Expected end: 15/04/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI ALLERONA
- Beneficiary
- REGIONE UMBRIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Natura e biodiversita'