CUP: J83E18000010005
Realizzazione Pista Ciclabile "Massa Superiore" di collegamento tra i Comuni di Castelmassa e Castelnovo Bariano"
SUMMARY OF THE PROJECT
Realizzazione Pista Ciclabile "Massa Superiore" di collegamento tra i Comuni di Castelmassa e Castelnovo Bariano"
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 1,799,848.80
of which cohesion funds
€ 1,445,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1445000.00 |
Municipality | 354848.80 |
Payments monitored
€ 1,223,099.68
of which cohesion funds
€ 895,235.51
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 750839.98 | 750839.98 | 41 |
2024 | 364238.60 | 1115078.58 | 61 |
2025 | 108021.10 | 1223099.68 | 67 |
State of progress
Open
Expected start: 30/03/2023
Effective start: 31/01/2023
Expected end: 31/07/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI CASTELMASSA
- Beneficiary
- REGIONE DEL VENETO
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,445,000.00
- Payments on cohesion funds
- € 895,235.51
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Natura e biodiversita'