CUP: H31B18000550001
Green Tour-Realizzazione pista ciclabile sul sedime dell'ex Ferrovia Militare Treviso-Ostiglia-Primo stralcio nel Tratto della Provincia di Vicenza
SUMMARY OF THE PROJECT
Realizzazione pista ciclabile
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 30,000 num
- Achieved
- 30,000 num
Download project
Funding monitored
€ 2,000,000.00
of which cohesion funds
€ 1,800,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1800000.00 |
Region | 200000.00 |
- Other resources - To be found:
- € 223,000
Payments monitored
€ 1,526,291.53
of which cohesion funds
€ 1,526,236.81
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 61302.74 | 61302.74 | 3 |
2023 | 327995.60 | 389298.34 | 19 |
2024 | 1136993.19 | 1526291.53 | 76 |
State of progress
Open
Expected start: 01/11/2022
Effective start: 12/01/2023
Expected end: 30/06/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- VENETO STRADE S.P.A.
- Beneficiary
- REGIONE DEL VENETO
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,800,000.00
- Payments on cohesion funds
- € 1,526,236.81
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Natura e biodiversita'