CUP: F71B18000190006
COMPLETAMENTO PISTE CICLABILI LUNGO SS. 9 VIA EMILIA
SUMMARY OF THE PROJECT
REALIZZAZIONE DI DUE TRATTI DI PISTA CICLABILE IN AMBITO URBANO E EXTRAURBANO: LOTTO 1 PISTA CICLABILE LUNGO VIA EMILIA PER FORLI LOTTO 2 PISTA CICLABILE DI COLLEGAMENTO TRA FORLIMPOPOLI E BERTINORO E RELATIVE FERMATE DELL'AUTOBUS
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 13,282 num
- Achieved
- 13,282 num
Download project
Funding monitored
€ 321,982.77
of which cohesion funds
€ 321,982.77
Given name | Amount |
---|---|
Development and Cohesion Fund | 321982.77 |
Payments monitored
€ 314,873.10
of which cohesion funds
€ 314,873.10
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 31317.56 | 31317.56 | 9 |
2021 | 190786.54 | 222104.10 | 68 |
2022 | 60818.20 | 282922.30 | 87 |
2023 | 31950.80 | 314873.10 | 97 |
State of progress
Settled
Expected start: 20/03/2020
Effective start: 03/05/2020
Expected end: 31/05/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI FORLIMPOPOLI
- Beneficiary
- REGIONE EMILIA-ROMAGNA
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 321,982.77
- Payments on cohesion funds
- € 314,873.10
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Natura e biodiversita'