CUP: I51E18000030006
Parco Termale
SUMMARY OF THE PROJECT
Riqualificazione e rigenerazione di parco urbano esistente e completamento di rete ciclopedonale cittadina
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 20,000 num
- Achieved
- 20,000 num
Download project
Funding monitored
€ 1,000,000.00
of which cohesion funds
€ 1,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1000000.00 |
Payments monitored
€ 1,000,000.00
of which cohesion funds
€ 1,000,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2017 | 8962.27 | 8962.27 | 0 |
2018 | 18024.31 | 26986.58 | 2 |
2019 | 1208.49 | 28195.07 | 2 |
2020 | 12560.37 | 40755.44 | 4 |
2021 | 638125.38 | 678880.82 | 67 |
2022 | 203185.58 | 882066.40 | 88 |
2023 | 0 | 882066.40 | 88 |
2024 | 117933.60 | 1000000.00 | 100 |
State of progress
Completed
Expected start: 25/01/2021
Effective start: 11/01/2021
Expected end: 14/03/2022
Effective end: 14/03/2022
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- COMUNE DI SALSOMAGGIORE TERME
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,000,000.00
- Payments on cohesion funds
- € 1,000,000.00
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici