CUP: I91D18000020002
IL NUOVO CENTRO CIVICO PER LA RIGENERAZIONE URBANA: RIQUALIFICAZIONE EDIFICIO IN PIAZZA FELICE FORESTI A CONSELICE
SUMMARY OF THE PROJECT
LA RIQUALIFICAZIONE DELL¿EDIFICIO PREVEDE INTERVENTI IMPRONTATI ALLA SOSTENIBILITà AMBIENTALE, AL MIGLIORAMENTO DELL¿EFFICIENZA ENERGETICA E DELLA SICUREZZA, AL CONTENIMENTO DEI COSTI DI GESTIONE. LE FUNZIONI DEL CENTRO CIVICO CHE VERRANNO INSEDIATE SI SINTETIZZANO IN TRE PRINCIPALI MODELLI: URBAN CENTRE, CREATIVE HUB, CO-WORKING SPACE. LE OPERE PREVISTE NEL PROGETTO PREVEDONO: OPERE EDILI, IMPIANTI MECCANICI, IMPIANTI ANTINCENDIO, IMPIANTI ELETTRICI, FOTOVOLTAICO.
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 100 num
- Achieved
- 100 num
Download project
Funding monitored
€ 924,000.00
of which cohesion funds
€ 924,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 924000.00 |
Payments monitored
€ 879,137.33
of which cohesion funds
€ 879,137.32
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 8856.05 | 8856.05 | 0 |
2019 | 248737.99 | 257594.04 | 27 |
2020 | 16573.64 | 274167.68 | 29 |
2021 | 19820.66 | 293988.34 | 31 |
2022 | 248317.09 | 542305.43 | 58 |
2023 | 336831.90 | 879137.33 | 95 |
State of progress
Completed
Expected start: 31/01/2023
Effective start: 24/02/2022
Expected end: 31/12/2023
Effective end: 30/11/2023
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- COMUNE DI CONSELICE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Riqualificazione urbana
- Sector of intervention
- Edilizia e spazi pubblici