CUP: J67F22000040001
MANUTENZIONE STRAORDINARIA DELLA STRUTTURA PORTUALE - PORTO DI NUMANA - COMPLETAMENTO RIFIORIMENTO
SUMMARY OF THE PROJECT
COMPLETAMENTO DEL PRECEDENTE PROGETTO DI RIFIORIMENTO SCOGLIERA DELLA DIGA FORANEA
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 780,000 num
- Achieved
- 650,000 num
Funding monitored
€ 103,786.50
of which cohesion funds
€ 103,786.50
Given name | Amount |
---|---|
Development and Cohesion Fund | 103786.50 |
Payments monitored
€ 103,648.24
of which cohesion funds
€ 103,648.24
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 103648.24 | 103648.24 | 99 |
State of progress
Completed
Expected start: 01/11/2022
Effective start: 23/11/2022
Expected end: 31/12/2022
Effective end: 20/12/2022
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI NUMANA
- Beneficiary
- REGIONE MARCHE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto marittimo