CUP: D54H13000820005
¿Riqualificazione della banchina e dei piazzali in radice del Molo Polisettoriale¿
SUMMARY OF THE PROJECT
Ristrutturazione della banchina in radice del Molo Polisettoriale e rifacimento dei piazzali retrostanti
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 500 num
- Achieved
- 500 num
Download project
Funding monitored
€ 9,219,145.21
of which cohesion funds
€ 9,219,145.21
Given name | Amount |
---|---|
Development and Cohesion Fund | 9219145.21 |
- Economies:
- € 5,780,854.79
Payments monitored
€ 9,219,145.21
of which cohesion funds
€ 9,219,145.21
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2013 | 1867.72 | 1867.72 | 0 |
2014 | 7573.29 | 9441.01 | 0 |
2015 | 2119.75 | 11560.76 | 0 |
2016 | 8107.45 | 19668.21 | 0 |
2017 | 1498337.62 | 1518005.83 | 16 |
2018 | 4049619.87 | 5567625.70 | 60 |
2019 | 3068407.10 | 8636032.80 | 93 |
2020 | 576932.76 | 9212965.56 | 99 |
2021 | 6179.65 | 9219145.21 | 100 |
State of progress
Completed
Expected start: 27/10/2017
Effective start: 27/10/2017
Expected end: 19/12/2018
Effective end: 07/02/2019
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- AUTORITA' DI SISTEMA PORTUALE DEL MAR IONIO
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 9,219,145.21
- Payments on cohesion funds
- € 9,219,145.21
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto marittimo