CUP: G74E20000010001
Allargamento della via Bondanello in Comune di Castel Maggiore (BO)
SUMMARY OF THE PROJECT
Allargamento della via Bondanello e costruzione pista ciclopedonale
Implementation indicator
Beneficiari/Popolazione Beneficiaria
- Target
- 1,000 num
- Achieved
- 1,000 num
Download project
Funding monitored
€ 1,430,000.00
of which cohesion funds
€ 1,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1000000.00 |
Municipality | 430000.00 |
Payments monitored
€ 1,301,391.22
of which cohesion funds
€ 910,062.62
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 14669.65 | 14669.65 | 1 |
2022 | 14485.58 | 29155.23 | 2 |
2023 | 638281.52 | 667436.75 | 46 |
2024 | 633954.47 | 1301391.22 | 91 |
State of progress
Open
Expected start: 01/03/2023
Effective start: 11/04/2023
Expected end: 16/06/2024
Effective end: 16/06/2024
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- COMUNE DI CASTEL MAGGIORE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,000,000.00
- Payments on cohesion funds
- € 910,062.62
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale