CUP: G95E18000180001
Diga Pietrarossa - Interventi per il completamento della diga
SUMMARY OF THE PROJECT
Intervento commissariato ex art.4 del decreto-legge n.32/2019 e nomina con DPCM 16 aprile 2021. Interventi per il completamento dello sbarramento e per la stabilizzazione delle sponde del serbatoio.
Download project
Funding monitored
€ 60,000,000.00
of which cohesion funds
€ 60,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 60000000.00 |
Payments monitored
€ 2,207,644.18
of which cohesion funds
€ 2,207,644.18
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: not available
Effective start: not available
Expected end: not available
Effective end: not available
Entities
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 60,000,000.00
- Payments on cohesion funds
- € 2,207,644.18
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Risorse idriche