CUP: H19J18000100002
ADEGUAMENTO E MESSA IN SICUREZZA DELLA VIABILITÃ INTERCOMUNALE TRA I COMUNI DI STELLA CILENTO- CASAL VELINO- POLLICA- OMIGNANO- SESSA CILENTO- LUSTRA
SUMMARY OF THE PROJECT
ADEGUAMENTO E MESSA IN SICUREZZA DELLA VIABILITÃ INTERCOMUNALE TRA I COMUNI DI STELLA CILENTO- CASAL VELINO- POLLICA- OMIGNANO- SESSA CILENTO- LUSTRA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 48 km
- Achieved
- 0.50 km
Funding monitored
€ 3,000,000.00
of which cohesion funds
€ 3,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3000000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 15/02/2022
Effective start: 22/02/2022
Expected end: 30/09/2022
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI STELLA CILENTO
- Beneficiary
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico