CUP: F62B18000210006
LAVORI DI SISTEMAZIONE DI VIA CESELLE
SUMMARY OF THE PROJECT
LAVORI DI SISTEMAZIONE DI VIA CESELLE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.34 km
- Achieved
- 0.34 km
Funding monitored
€ 451,338.74
of which cohesion funds
€ 451,338.74
Given name | Amount |
---|---|
Development and Cohesion Fund | 451338.74 |
Payments monitored
€ 443,555.41
of which cohesion funds
€ 443,555.41
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 16774.28 | 16774.28 | 3 |
2020 | 210198.07 | 226972.35 | 50 |
2021 | 152162.76 | 379135.11 | 84 |
2022 | 64420.30 | 443555.41 | 98 |
State of progress
Completed
Expected start: 09/09/2019
Effective start: 09/09/2019
Expected end: 14/06/2021
Effective end: 14/06/2021
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI ANACAPRI
- Beneficiary
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico