CUP: F37H18001090001
Riqualificazione di via Giovanni Paolo II e opere di mitigazione ambientale - Lotto Funzionale I
SUMMARY OF THE PROJECT
Riqualificazione di via Giovanni Paolo II e opere di mitigazione ambientale - Lotto Funzionale I
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1.01 km
- Achieved
- 1.01 km
Download project
Funding monitored
€ 2,508,962.89
of which cohesion funds
€ 2,508,962.89
Given name | Amount |
---|---|
Development and Cohesion Fund | 2508962.89 |
Payments monitored
€ 2,351,284.15
of which cohesion funds
€ 2,348,015.92
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 29182.40 | 29182.40 | 1 |
2019 | 19208.00 | 48390.40 | 1 |
2020 | 822574.21 | 870964.61 | 34 |
2021 | 1114873.01 | 1985837.62 | 79 |
2022 | 365446.53 | 2351284.15 | 93 |
State of progress
Open
Expected start: 07/05/2020
Effective start: 07/05/2020
Expected end: 15/02/2022
Effective end: 09/03/2022
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI ACERRA
- Beneficiary
- REGIONE CAMPANIA
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 2,508,962.89
- Payments on cohesion funds
- € 2,348,015.92
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico