CUP: F97H18002630002
SISTEMAZIONE STRADA RURALE CAMEROTA CAPOLUOGO - LENTISCOSA E REALIZZAZIONE DEL PONTE DI ATTRAVERSAMENTO SUL VALLONE DELLE FORNACI
SUMMARY OF THE PROJECT
SISTEMAZIONE STRADA RURALE CAMEROTA CAPOLUOGO - LENTISCOSA E REALIZZAZIONE DEL PONTE DI ATTRAVERSAMENTO SUL VALLONE DELLE FORNACI
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 2.28 km
- Achieved
- 0 km
Download project
Funding monitored
€ 1,042,321.18
of which cohesion funds
€ 1,042,321.18
Given name | Amount |
---|---|
Development and Cohesion Fund | 1042321.18 |
Payments monitored
€ 108,594.37
of which cohesion funds
€ 108,564.37
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 3600.00 | 3600.00 | 0 |
2020 | 104994.37 | 108594.37 | 10 |
State of progress
Open
Expected start: 18/05/2020
Effective start: not available
Expected end: 19/01/2021
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI CAMEROTA
- Beneficiary
- REGIONE CAMPANIA
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,042,321.18
- Payments on cohesion funds
- € 108,564.37
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico