SS.N. 106 JONICA (TRACCIATO ESISTENTE) - TRATTA CROTONE (BIVIO PASSOVECCHIO) KM 256+000 - SIBARI KM 329+000 - MESSA IN SICUREZZA - 3° TRONCO (STRALCIO)
L¿INTERVENTO IN QUESTIONE PREVEDE LA SISTEMAZIONE E MESSA IN SICUREZZA, QUASI SEMPRE IN SEDE AD ECCEZIONE DELL¿ATTRAVERSAMENTO DI MELISSA, DEL TRATTO DELL¿ATTUALE TRACCIATO DELLA SS 106 FRA LOCALITà GABELLA AL KM 256 CIRCA - DOVE TERMINANO I 4 KM GIà AMMODERNATI A 4 CORSIE CHE PARTONO DA CROTONE SVINCOLO PASSOVECCHIO ED IL KM 290+200 CIRCA IN COMUNE DI CIRò. IN TALE TRATTO DELLA JONICA, CHE SVILUPPA CIRCA 34 KM, OGGI PREVALE UNA SEZIONE AMPIA NON PIù DI 7.50 M, INADEGUATA E POCO SICURA. DOPO I NUMEROSI INTERVENTI DI MESSA IN SICUREZZA DI VARIE INTERSEZIONI CON LA STATALE GIà APPALTATI, SI INTENDE ORA PASSARE ALLA SISTEMAZIONE DELL¿ASSE STRADALE E SI PREVEDE DI PORTARE LA SEZIONE STRADALE AI 10.50 M DELLA CATEGORIA C1 DELLE VIGENTI NORME, PREDISPORRE QUALCHE VARIANTE LOCALE IN CORRISPONDENZA DEI CENTRI ABITATI SIGNIFICATIVI OLTRE AD EVENTUALI RETTIFICHE DI TRACCIATO E INTERVENTI DI MANUTENZIONE ORDINARIA O STRAORDINARIA PER LE OPERE PRESENTI LUNGO IL TRACCIATO. CON I FINANZIA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 30 km
- Achieved
- 0 km
Given name | Amount |
---|---|
Development and Cohesion Fund | 5700000.00 |
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 1104863.49 | 1104863.49 | 19 |
2023 | 137589.80 | 1242453.29 | 21 |
2024 | 142392.67 | 1384845.96 | 24 |
State of progress
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 5,700,000.00
- Payments on cohesion funds
- € 1,384,845.96
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico