CUP: B41B20000910001
Messa in sicurezza conoide strada regionale n.28
SUMMARY OF THE PROJECT
Messa in sicurezza conoide strada regionale n.28
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.20 km
- Achieved
- 0.20 km
Download project
Funding monitored
€ 1,157,247.19
of which cohesion funds
€ 1,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1000000.00 |
Another public source | 157247.19 |
Payments monitored
€ 212,353.03
of which cohesion funds
€ 212,353.03
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/06/2022
Effective start: 26/04/2023
Expected end: 30/09/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- REGIONE AUTONOMA VALLE D'AOSTA
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 1,000,000.00
- Payments on cohesion funds
- € 212,353.03
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico
Other projects in territory
Same type of investment
banda Ultralarga nelle aree bianche del territorio della Regione Valle d'Aosta con FONDI FSC | € 4,594,780 |