CUP: D21B18000160002
LAVORI DI COSTRUZIONE STRADA DI COLLEGAMENTO VIA CARDUCCI - VIA D'ANNUNZIO - OPERE DI COMPLETAMENTO
SUMMARY OF THE PROJECT
LAVORI DI COSTRUZIONE STRADA DI COLLEGAMENTO VIA CARDUCCI - VIA D'ANNUNZIO - OPERE DI COMPLETAMENTO
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 3.50 km
- Achieved
- 1.90 km
Download project
Funding monitored
€ 693,962.14
of which cohesion funds
€ 693,962.14
Given name | Amount |
---|---|
Development and Cohesion Fund | 693962.14 |
Payments monitored
€ 477,918.66
of which cohesion funds
€ 477,918.66
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 15334.15 | 15334.15 | 2 |
2022 | 204420.41 | 219754.56 | 31 |
2023 | 258164.10 | 477918.66 | 68 |
State of progress
Open
Expected start: 25/11/2021
Effective start: 25/11/2021
Expected end: 31/03/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI RECALE
- Beneficiary
- REGIONE CAMPANIA
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 693,962.14
- Payments on cohesion funds
- € 477,918.66
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico