CUP: D43D17000770001
Opere di completamento del consolidamento strada comunale via Alba
SUMMARY OF THE PROJECT
manutenzione strordinaria della strada
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 320,000.00
of which cohesion funds
€ 320,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 320000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/03/2022
Effective start: 30/03/2023
Expected end: 30/06/2023
Effective end: 03/10/2023
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI DIANO D'ALBA
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 320,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico