CUP: E47H18003180003
SP 129 RIPRISTINO CORPO STRADALE AL KM 2+000 CIRCA IN COMUNE DI CERRETO GRUE
SUMMARY OF THE PROJECT
RIPRISTINO DEL CORPO STRADALE IN FRANA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Funding monitored
€ 450,000.00
of which cohesion funds
€ 450,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 450000.00 |
Payments monitored
€ 11,376.50
of which cohesion funds
€ 11,376.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 11376.50 | 11376.50 | 2 |
State of progress
Open
Expected start: 31/12/2022
Effective start: not available
Expected end: 31/07/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI ALESSANDRIA
- Beneficiary
- REGIONE PIEMONTE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico