CUP: I87H18001200001
SP VARIE ¿ INTERVENTI DI RIPRISTINO STRUTTURALE E CONSOLIDAMENTO SU PONTI NEL REPARTO DI ALBA E MONDOVì
SUMMARY OF THE PROJECT
RIMOZIONE E ASPORTAZIONE COMPLETA DEGLI ESISTENTI DISPOSITIVI DI DILATAZIONE E DEL MATERIALE ACCUMULATO NELLE INTERCAPEDINI ADIBITE A GIUNTO; FORNITURA E POSA DI GIUNTI DI DILATAZIONE IN GOMMA ARMATA O PETTINE PER IMPALCATI DI IDONEE DIMENSIONI; FORNITURA E POSA DI GIUNTI TAMPONE; FORNITURA E POSA DI COPRIGIUNTI.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.50 km
- Achieved
- 0.50 km
Download project
Funding monitored
€ 148,958.31
of which cohesion funds
€ 148,958.31
Given name | Amount |
---|---|
Development and Cohesion Fund | 148958.31 |
Payments monitored
€ 148,958.31
of which cohesion funds
€ 148,958.31
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 230.00 | 230.00 | 0 |
2020 | 148728.31 | 148958.31 | 100 |
State of progress
Completed
Expected start: 06/12/2019
Effective start: 06/12/2019
Expected end: 31/08/2020
Effective end: 01/07/2020
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI CUNEO
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 148,958.31
- Payments on cohesion funds
- € 148,958.31
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico