CUP: D67H18000630002
LAVORI DI MESSA IN SICUREZZA DELLA RETE STRADALE PROVINCIALE MEDIANTE INTERVENTI DI RIFACIMENTO COMPLETO DELLA SOVRASTRUTTURA STRADALE. LOTTO 1
SUMMARY OF THE PROJECT
Realizzazione di tratti di bitumatura
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 5.90 km
- Achieved
- 5.90 km
Download project
Funding monitored
€ 504,725.00
of which cohesion funds
€ 504,725.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 504725.00 |
Payments monitored
€ 464,496.12
of which cohesion funds
€ 464,496.12
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 464496.12 | 464496.12 | 92 |
State of progress
Open
Expected start: 02/05/2019
Effective start: 02/05/2019
Expected end: 30/06/2019
Effective end: 14/10/2019
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI VERCELLI
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 504,725.00
- Payments on cohesion funds
- € 464,496.12
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico