CUP: D86G18000530003
LAVORI DI MESSA IN SICUREZZA DELLA RETE STRADALE PROVINCIALE MEDIANTE SISTEMAZIONE DI VERSANTI
SUMMARY OF THE PROJECT
Interventi di sostituzione o nuova posa di reti in aderenza e/o barriere paramassi.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.20 km
- Achieved
- 0.20 km
Download project
Funding monitored
€ 100,000.00
of which cohesion funds
€ 100,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 100000.00 |
Payments monitored
€ 89,891.85
of which cohesion funds
€ 89,891.85
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 89891.85 | 89891.85 | 89 |
State of progress
Open
Expected start: 23/07/2019
Effective start: 23/07/2019
Expected end: 31/12/2019
Effective end: 31/12/2019
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI VERCELLI
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 100,000.00
- Payments on cohesion funds
- € 89,891.85
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico