STRADA PROVINCIALE N. 39 "DELLE DUE RIVIERE". CONSOLIDAMENTO DEI VERSANTI FRANATI A CAUSA DI DISSESTO IDROGEOLOGICO.
SUMMARY OF THE PROJECT
IL PROGETTO PER IL CONSOLIDAMENTO PREVEDE LA REALIZZAZIONE DI UNA TRAVE IN C.A. A FORMA DI L FONDATA SU MICROPALI DI LUNGHEZZA PARI A 9 M, DISPOSTI SU DUE FILE, IN MODO DA COSTITUIRE SIA LA BASE DELLA SUCCESSIVA RICARICA DELLA SEDE STRADALE, SIA UN MURETTO DI CONTENIMENTO SU CUI SARÃ POSATA UNA BARRIERA STRADALE TIPO H2 BORDO PONTE IN ACCIAIO CORTEN.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1,000 km
- Achieved
- 1,000 km
Download project
Funding monitored
€ 200,000.00
of which cohesion funds
€ 200,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 200000.00 |
Payments monitored
€ 196,798.10
of which cohesion funds
€ 195,615.98
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 13812.84 | 13812.84 | 6 |
2020 | 30.00 | 13842.84 | 6 |
2021 | 182955.26 | 196798.10 | 98 |
State of progress
Completed
Expected start: 02/12/2019
Effective start: 26/10/2020
Expected end: 31/03/2020
Effective end: 02/04/2021
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI NOVARA
- Beneficiary
- REGIONE PIEMONTE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 200,000.00
- Payments on cohesion funds
- € 195,615.98
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico