CUP: E97H19002020001
SP 222 PONTE IN C/A E ACCIAIO SU TORRENTE ERRO
SUMMARY OF THE PROJECT
SOSTITUZIONE BARRIERE STRADALI, RIPRISTINO COPRIFERRI E SPALLE
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Download project
Funding monitored
€ 550,000.00
of which cohesion funds
€ 550,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 550000.00 |
Payments monitored
€ 48,315.62
of which cohesion funds
€ 48,315.62
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 48315.62 | 48315.62 | 8 |
State of progress
Open
Expected start: 31/01/2024
Effective start: not available
Expected end: 31/03/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI ALESSANDRIA
- Beneficiary
- REGIONE PIEMONTE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico