CUP: J97H19001240002
S.P. N. 6 DI PINEROLO. INTERVENTI DI RIPRISTINO DELLA BARRIERE DI PROTEZIONE A TRATTI SALTUARI DAL KM 12+500 AL KM 19+500.
SUMMARY OF THE PROJECT
INTERVENTO DI SOSTITUZIONE ED INTEGRAZIONE DELLE BARRIERE STRADALI LUNGO LA S.P 6 A TRATTI SALTUARI.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1.20 km
- Achieved
- 1.20 km
Download project
Funding monitored
€ 250,000.00
of which cohesion funds
€ 250,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 250000.00 |
Payments monitored
€ 213,162.07
of which cohesion funds
€ 213,162.07
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 118566.64 | 118566.64 | 47 |
2022 | 94595.43 | 213162.07 | 85 |
State of progress
Open
Expected start: 06/09/2021
Effective start: 13/09/2021
Expected end: 11/12/2021
Effective end: 11/12/2021
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- CITTA METROPOLITANA DI TORINO
- Beneficiary
- REGIONE PIEMONTE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico