CUP: F37H18004040002
LAVORI DI RIPRISTINO CORPO STRADALE LUNGO LA SP 105 "ANDORNO MICCA-MOSSO" AL KM. 12+400 - FRAZIONE PISTOLESA IN COMUNE DI VEGLIO
SUMMARY OF THE PROJECT
LAVORI DI MANUTENZIONE STRAORDINARIA
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Funding monitored
€ 450,000.00
of which cohesion funds
€ 450,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 450000.00 |
Payments monitored
€ 353,109.69
of which cohesion funds
€ 353,109.69
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 21829.31 | 21829.31 | 4 |
2021 | 271811.13 | 293640.44 | 65 |
2022 | 59469.25 | 353109.69 | 78 |
State of progress
Open
Expected start: 08/04/2021
Effective start: 08/04/2021
Expected end: 23/11/2021
Effective end: 23/11/2021
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI BIELLA
- Beneficiary
- REGIONE PIEMONTE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico