CUP: I17H19001180002
S.P. N. 184 TR. FOSSANO - LEVALDIGI. LAVORI DI SISTEMAZIONE ED ALLARGAMENTO DEL TRACCIATO.
SUMMARY OF THE PROJECT
OPERE DI ADEGUAMENTO DELLA PIATTAFORMA STRADALE DI UN TRATTO DI CIRCA 1 KM DELLA S.P. N. 184 TR. LEVALDIGI ¿ FOSSANO. IL TRACCIATO IN PROGETTO COINCIDE PER LA QUASI TOTALITà DEL SUO SVILUPPO CON IL TRACCIATO ESISTENTE. AL FINE DEL RISPETTO DELLA NORMATIVA SULLA PROGETTAZIONE DELLE STRADE, IN CORRISPONDENZA DELLE CURVE Ê STATO NECESSARIO PREVEDERE UNA ADEGUAMENTO ALLE INDICAZIONI DI NORMATIVA.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Funding monitored
€ 1,157,148.57
of which cohesion funds
€ 1,157,148.57
Given name | Amount |
---|---|
Development and Cohesion Fund | 1157148.57 |
Payments monitored
€ 758,023.76
of which cohesion funds
€ 758,023.76
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 4343.91 | 4343.91 | 0 |
2022 | 7833.13 | 12177.04 | 1 |
2023 | 683843.34 | 696020.38 | 60 |
2024 | 62003.38 | 758023.76 | 65 |
State of progress
Open
Expected start: 02/08/2021
Effective start: 07/04/2022
Expected end: 01/03/2022
Effective end: 05/10/2023
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI CUNEO
- Beneficiary
- REGIONE PIEMONTE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico