CUP: G67H19000000002
LAVORI DI RIPRISTINO E MESSA IN SICUREZZA, DELLA SP94 PONTE CASALDUNI I° LOTTO SEZ. 1 - SEZ.67
SUMMARY OF THE PROJECT
LAVORI DI RIPRISTINO E MESSA IN SICUREZZA, DELLA SP94 PONTE CASALDUNI I° LOTTO SEZ. 1 - SEZ.67
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1.96 km
- Achieved
- 1.96 km
Funding monitored
€ 3,000,000.00
of which cohesion funds
€ 3,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3000000.00 |
Payments monitored
€ 2,682,273.75
of which cohesion funds
€ 2,682,273.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 299588.82 | 299588.82 | 9 |
2020 | 2221685.57 | 2521274.39 | 84 |
2021 | 45282.48 | 2566556.87 | 85 |
2022 | 31968.03 | 2598524.90 | 86 |
2023 | 83748.85 | 2682273.75 | 89 |
State of progress
Open
Expected start: 04/11/2019
Effective start: 05/02/2020
Expected end: 27/02/2023
Effective end: 27/02/2023
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI CASALDUNI
- Beneficiary
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico