Regimazione Idraulica e formazione di cunette in cls, previa pulizia scarpata a difesa del corpo stradale lungo le SS.SS. del CM B
SUMMARY OF THE PROJECT
Regimazione Idraulica e formazione di cunette in cls, previa pulizia scarpata a difesa del corpo stradale lungo le SS.SS. del CM B
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 10 km
- Achieved
- 0 km
Download project
Funding monitored
€ 937,000.00
of which cohesion funds
€ 937,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 937000.00 |
Payments monitored
€ 123,377.63
of which cohesion funds
€ 123,377.63
13%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 123377.63 | 123377.63 | 13 |
State of progress
Open
Expected start: 22/03/2023
Effective start: 22/03/2023
Expected end: 29/01/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS - SOCIETA' PER AZIONI
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 937,000.00
- Payments on cohesion funds
- € 123,377.63
- Policy Area
- Ambiente e risorse naturali
- Sector of intervention
- Rischi e adattamento climatico