Ferrovie del Gargano - Fornitura di n. 1 elettrotreno a composizione bloccta (M+R+M)
SUMMARY OF THE PROJECT
Ferrovie del Gargano - Fornitura di n. 1 elettrotreno a composizione bloccta (M+R+M)
Implementation indicator
Unita' beni acquistati
- Target
- 1 num
- Achieved
- 0 num
Download project
Funding monitored
€ 6,250,000.00
of which cohesion funds
€ 6,250,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 6250000.00 |
Payments monitored
€ 5,892,750.00
of which cohesion funds
€ 5,892,750.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 607500.00 | 607500.00 | 9 |
2023 | 0 | 607500.00 | 9 |
2024 | 5285250.00 | 5892750.00 | 94 |
State of progress
Open
Expected start: 31/05/2022
Effective start: 31/05/2022
Expected end: 31/12/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- Ferrovie del Gargano srl
- Beneficiary
- REGIONE PUGLIA
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 6,250,000.00
- Payments on cohesion funds
- € 5,892,750.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana