CUP: F51J22000230001
METROPOLITANA AREA VASTA DI CAGLIARI: TRATTA CARACALLA/DELL¿ARGINE
SUMMARY OF THE PROJECT
L¿INTERVENTO PREVEDE LA REALIZZAZIONE DELL¿ESTENSIONE DELLA RETE DI METROPOLITANA LEGGERA DI CAGLIARI COLLEGANDO, IN DOPPIO BINARIO DI CUI PARTE IN VIADOTTO, LA FERMATA CARACALLA ALLA FERMATA DELL¿ARGINE. L¿INTERVENTO Ê COMPRENSIVO DI UN SISTEMA DI SEGNALAMENTO E GESTIONE DEL TRAFFICO TALE DA ASSICURARE ¿ IN SICUREZZA ¿ LA PERFETTA COMPATIBILITà TRA LE LINEE IN ESERCIZIO.
Implementation indicator
Lunghezza totale delle linee tranviarie e metropolitane nuove o migliorate
- Target
- 1.76 km
- Achieved
- 0 km
Download project
Funding monitored
€ 23,000,000.00
of which cohesion funds
€ 23,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 23000000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 06/06/2024
Effective start: not available
Expected end: 31/12/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- ARST SPA
- Beneficiary
- REGIONE AUTONOMA DELLA SARDEGNA
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 23,000,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Mobilita' urbana