CUP: J74J17000010001
SFM5 FERMATA BORGATA QUAGLIA-LE GRU COLLEGAMENTO BORGATA LESNA
SUMMARY OF THE PROJECT
REALIZZAZIONE DI UNA FERMATA IN TRINCEA LUNGO L'ESISTENTE LINEA DA S. PAOLO A ORBASSANO CON CONNESSIONE SIA ALL'ABITATO SITO IN COMUNE DI GRUGLIASCO SIA ALLA BORGATA LESNA, SITA IN COMUNE DI TORINO
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 0 km
Funding monitored
€ 13,330,439.43
of which cohesion funds
€ 700,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 700000.00 |
Another public source | 12630439.43 |
- Other resources - Private:
- € 3,700,000
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 10/01/2023
Effective start: 10/01/2023
Expected end: 07/01/2026
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario