CUP: J44C19000040009
NODO COMPLESSO IN CORRISPONDENZA DELLA STAZIONE FS DI SALERNO CENTRALE
SUMMARY OF THE PROJECT
POTENZIAMENTO DEL PIANO REGOLATORE GENERALE DI STAZIONE CON REALIZZAZIONE MARCIAPIEDE A SERVIZIO DEL BINARIO VIII E PROLUNGAMENTO DELL'ATTUALE SOTTOPASSO; REALIZZAZIONE DI UNA ASTA DI MANOVRA LATO ARECHI/BATTIPAGLIA PER L'ACCESSO AGLI IMPIANTI DI RICOVERO TRENI; UPGRADING DELL'APPARATO DI STAZIONE E DEI SISTEMI DI INFORMAZIONE AL PUBBLICO, COMPRESO NUOVO SISTEMA IAP DELLA LINEA METROPOLITANA SALERNO - ARECHI
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 0 km
Funding monitored
€ 32,236,524.29
of which cohesion funds
€ 25,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 25000000.00 |
Another public source | 7236524.29 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 25/11/2020
Effective start: 25/11/2020
Expected end: 31/12/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario