PASSANTE FERROVIARIO DI NAPOLI - ADEGUAMENTO TECNOLOGIE
SUMMARY OF THE PROJECT
UPGRADE DEL SISTEMA DI CIRCOLAZIONE SULLA TRATTA POZZUOLI - NAPOLI GIANTURCO DELLA LINEA VILLA L. - NAPOLI S. GIOVANNI BARRA CON CONTESTUALE IMPÊLEMENTAZIONE DI TECNOLOGIE INNOVATIVE CHE CONSENTONO LA RIDUZIONE DEI TEMPO DI DISTANZIAMENTO TRA I TRENI
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 17.50 km
- Achieved
- 0 km
Download project
Funding monitored
€ 28,000,000.00
of which cohesion funds
€ 14,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 14000000.00 |
Another public source | 14000000.00 |
- Other resources - To be found:
- € 2,308,000
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 08/08/2023
Effective start: 08/08/2023
Expected end: 10/01/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario