CUP: J31J05000030011
NODO DI FALCONARA
SUMMARY OF THE PROJECT
ADEGUAMENTO DELLA PROGETTAZIONE DELLA FASE DI COMPLETAMENTO DEL NODO DI FALCONARA . LE OPERE CONCISTONO NELLA REALIZZAZIONE DELLA NUOVA STAZIONE DI MONTEMARCIANO CON TRASFORMAZIONE IN FERMATA DELL'ATTUALE STAZIONE DI CHIARAVALLE. INTERVENTO FINANZIATO PER LA SOLA PROGETTAZIONE
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 1.20 km
- Achieved
- 0 km
Download project
Funding monitored
€ 2,000,000.00
of which cohesion funds
€ 1,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1000000.00 |
Another public source | 1000000.00 |
- Other resources - To be found:
- € 3,000,000
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 28/12/2026
Effective start: not available
Expected end: 08/12/2028
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario