CUP: C31I19000020003
LINEA REGGIO EMILIA-CIANO D'ENZA: ELETTRIFICAZIONE
SUMMARY OF THE PROJECT
PROGETTAZIONE E REALIZZAZIONE DI NUOVI IMPIANTI DI TRAZIONE ELETTRICA CON TENSIONE PARI A 3 KV C.C. E RELATIVO SISTEMA DI ALIMENTAZIONE
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 26 km
- Achieved
- 26 km
Download project
Funding monitored
€ 11,600,000.00
of which cohesion funds
€ 800,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 800000.00 |
Region | 10800000.00 |
Payments monitored
€ 9,840,829.38
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 1170048.62 | 1170048.62 | 10 |
2021 | 5158133.90 | 6328182.52 | 54 |
2022 | 3512646.86 | 9840829.38 | 84 |
State of progress
Open
Expected start: 30/06/2020
Effective start: 03/02/2020
Expected end: 31/10/2022
Effective end: 05/09/2022
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- FERROVIE EMILIA ROMAGNA SOCIETA A RESPONSABILITA LIMITATATA IN SIGLA FER SRL
- Beneficiary
- REGIONE EMILIA-ROMAGNA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario