CUP: J74C20001660001
CHIUSURA ANELLO FERROVIARIO DI PALERMO TRATTA GIACHERY - POLITEAMA - NOTARBARTOLO
SUMMARY OF THE PROJECT
GLI INTERVENTI SONO FINALIZZATI AL COMPLETAMENTO DELLA RETE METROPOLITANA DI PALERMO. ATTUALMENTE Ê IN ESERCIZIO LA TRATTA TRA LE STAZIONI NOTARBARTOLO E GIACHERY MENTRE SONO IN CORSO I LAVORI PER IL PROLUNGAMENTO DELLA TRATTA GIACHERY - POLITEAMA. GLI INTERVENTI IN OGGETTO CONSISTONO NEL COMPLETAMENTO DELL'ANELLO NELLA TRATTA POLITEAMA - NOTARBARTOLO E DELLA FERMATA MALASPINA.
Implementation indicator
Lunghezza totale delle linee ferroviarie ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 0 km
Download project
Funding monitored
€ 141,800,400.04
of which cohesion funds
€ 100,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 100000000.00 |
Another public source | 41800400.04 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 06/04/2023
Effective start: 06/04/2023
Expected end: 03/01/2029
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- RETE FERROVIARIA ITALIANA SPA
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 100,000,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto ferroviario