CUP: C67H19001680001
RAZIONALIZZAZIONE INTERSEZIONE TRA LA S.P.219 ¿ETE MORTO¿ E LA S.P.9 ¿CAMPIGLIONESE¿
SUMMARY OF THE PROJECT
REALIZZAZIONE DI UN INTERVENTO DI RAZIONALIZZAZIONE DELLA VIABILITà ALL¿INTERSEZIONE TRA LE STRADE PROVINCIALI S.P.219 ¿ETE MORTO¿ E LA S.P.9 ¿CAMPIGLIONESE¿.
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 0.35 km
- Achieved
- 0.35 km
Download project
Funding monitored
€ 700,000.00
of which cohesion funds
€ 700,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 700000.00 |
Payments monitored
€ 62,938.34
of which cohesion funds
€ 62,938.34
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 6952.94 | 6952.94 | 0 |
2021 | 16256.16 | 23209.10 | 3 |
2022 | 39729.24 | 62938.34 | 8 |
State of progress
Open
Expected start: 01/02/2023
Effective start: 03/04/2023
Expected end: 04/10/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI FERMO
- Beneficiary
- REGIONE MARCHE
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 700,000.00
- Payments on cohesion funds
- € 62,938.34
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale