CUP: J81B18000310007
RISANAMENTO E ASFALTATURA STRADE DI ACCESSO AI MASI "KEGELBERG" (VANDOIES)
SUMMARY OF THE PROJECT
RISANAMENTO DI DIVERSI PERCORSI DI MONTAGNA NEL COMUNE DI VANDOIES - VIA "KEGELBERG". APPROVAZIONE DEL PROGETTO ESECUTIVO*VIA KEGELBERG*APPROVAZIONE DEL PROGETTO ESECUTIVO
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1.92 km
- Achieved
- 1.92 km
Download project
Funding monitored
€ 278,429.00
of which cohesion funds
€ 278,429.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 278429.00 |
- Economies:
- € 16,571.00
Payments monitored
€ 278,429.00
of which cohesion funds
€ 278,429.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 278429.00 | 278429.00 | 100 |
State of progress
Completed
Expected start: 11/02/2019
Effective start: 11/02/2019
Expected end: 19/10/2019
Effective end: 19/10/2019
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- PROVINCIA AUTONOMA DI BOLZANO
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 278,429.00
- Payments on cohesion funds
- € 278,429.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale