CUP: I67H21000700001
INTERVENTO DI OTTIMIZZAZIONE DELLA VIABILITÃ DELLA SP 207
SUMMARY OF THE PROJECT
ADEGUAMENTO E MESSA IN SICUREZZA DI TRATTI DELLA SP 207 "LUNGO TRONTO" MEDIANTE INTERVENTI SUI PONTI STRADALI AL KM 2+000 E AL KM 4+500 OLTRE CHE SU ALTRI TRATTI PUNTUALI.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 0 km
Funding monitored
€ 1,000,000.00
of which cohesion funds
€ 1,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 1000000.00 |
Payments monitored
€ 375.00
of which cohesion funds
€ 375.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 375.00 | 375.00 | 0 |
State of progress
Open
Expected start: 01/03/2023
Effective start: 07/04/2023
Expected end: 31/12/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- AMMINISTRAZIONE PROVINCIALE DI ASCOLI PICENO
- Beneficiary
- REGIONE MARCHE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale