CUP: E46G18000030002
LAVORI DI MESSA IN SICUREZZA STRADA TURISTICA DEL MONTE TERMINIO - EX SS 574
SUMMARY OF THE PROJECT
LAVORI DI MESSA IN SICUREZZA STRADA TURISTICA DEL MONTE TERMINIO - EX SS 574
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 30 km
- Achieved
- 0 km
Download project
Funding monitored
€ 2,862,962.33
of which cohesion funds
€ 2,862,962.33
Given name | Amount |
---|---|
Development and Cohesion Fund | 2862962.33 |
Payments monitored
€ 279,998.51
of which cohesion funds
€ 279,998.31
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 16084.76 | 16084.76 | 0 |
2020 | 263913.75 | 279998.51 | 9 |
State of progress
Open
Expected start: 29/01/2020
Effective start: 29/01/2020
Expected end: 15/12/2020
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI SERINO
- Beneficiary
- REGIONE CAMPANIA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale
Other projects in territory
Same theme
INTERVENTI DI MESSA IN SICUREZZA STRADE COMUNALI | € 63,840 |