CUP: F87H19001260001
CORRIDOIO POTENZA,TITO-BRIENZA, A3 - LAGONEGRESE CON PROLUNGAMENTO ALLA MELFI-CANDELA-SS 658: S.S. 658 NUOVO ITINERARIO POTENZA-MELFI - LAVORI DI MESSA IN SICUREZZA DEL TRACCIATO STRADALE IN TRATTI SALTUARI TRA I KM 0+000 E IL KM 48+131 - 2° STRALCIO).LAVORI DI M.S. PER IL RIPRISTINO ED IL RISANAMENTO CORTICALE DELLE STRUTTURE DEI VIADOTTI AGROMONTE AL KM 29+320 E STRASCINATI AL KM 30+558 DELLA S.S. N° 658 "POTENZA-MELFI"
SUMMARY OF THE PROJECT
L'INTERVENTO PREVEDEIL RIPRISTINO ED IL RISANAMENTO CORTICALE DELLE STRUTTURE DEI VIADOTTI AGROMONTE AL KM 29+320 E STRASCINATI AL KM 30+558 DELLA S.S. N° 658 "POTENZA-MELFI", NELL'AMBITO DEL PROGETTO EX PZ143 DI RIQUALIFICAZIONE DELL¿INTERO TRACCIATO STRADALE FINO AL KM 48+131 FINALIZZATO AL MIGLIORAMENTO DELLA SICUREZZA STRADALE MEDIANTE INTERVENTI DI MANUTENZIONE STRAORDINARIA SULLE OPERE D¿ARTE, SULLA PAVIMENTAZIONE, SULLE BARRIERE DI SICUREZZA E SUL CORPO STRADALE.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 48 km
- Achieved
- 24 km
Download project
Funding monitored
€ 3,700,000.00
of which cohesion funds
€ 3,700,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3700000.00 |
Payments monitored
€ 2,062,126.81
of which cohesion funds
€ 2,062,126.81
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 495793.99 | 495793.99 | 13 |
2022 | 1464820.44 | 1960614.43 | 52 |
2023 | 101512.38 | 2062126.81 | 55 |
State of progress
Open
Expected start: 26/07/2021
Effective start: 26/07/2021
Expected end: 30/08/2023
Effective end: 30/08/2023
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale