CUP: F67H19000860001
CORRIDOIO POTENZA,TITO-BRIENZA, A3 - LAGONEGRESE CON PROLUNGAMENTO ALLA MELFI-CANDELA-SS 658: S.S. 658 NUOVO ITINERARIO POTENZA-MELFI - LAVORI DI MESSA IN SICUREZZA DEL TRACCIATO STRADALE IN TRATTI SALTUARI TRA I KM 0+000 E IL KM 48+131 - 2° STRALCIO).LAVORI DI M.S. PER IL RIPRISTINO ED IL RISANAMENTO CORTICALE DELLE STRUTTURE E L'IMPERMEABILIZZAZIONE DELL'IMPALCATO DEI VIADOTTI BOSCO AL KM 13+555, CESARACCHIO AL KM 14+020 E GIACONELLI AL KM 45+270 DELLA S.S. N° 658 "POTENZA-MELFI"
SUMMARY OF THE PROJECT
L'INTERVENTO PREVEDE IL RIPRISTINO ED IL RISANAMENTO CORTICALE DELLE STRUTTURE E L'IMPERMEABILIZZAZIONE DELL'IMPALCATO DEI VIADOTTI BOSCO AL KM 13+555, CESARACCHIO AL KM 14+020 E GIACONELLI AL KM 45+270 DELLA S.S. N° 658 "POTENZA-MELFI", NELL'AMBITO DEL PROGETTO EX PZ143 DI RIQUALIFICAZIONE DELL INTERO TRACCIATO STRADALE FINO AL KM 48+131 FINALIZZATO AL MIGLIORAMENTO DELLA SICUREZZA STRADALE MEDIANTE INTERVENTI DI MANUTENZIONE STRAORDINARIA SULLE OPERE D ARTE, SULLA PAVIMENTAZIONE, SULLE BARRIERE DI SICUREZZA E SUL CORPO STRADALE.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 32 km
- Achieved
- 0 km
Funding monitored
€ 4,500,000.00
of which cohesion funds
€ 4,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 4500000.00 |
Payments monitored
€ 15,350.54
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 15350.54 | 15350.54 | 0 |
State of progress
Open
Expected start: 01/05/2024
Effective start: not available
Expected end: 31/12/2025
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale