CUP: F41B16000380001
SS. N.115 SUD OCCIDENTALE SICULA: VARIANTE NEL TRATTO COMPRESO FRA LO SVINCOLO DI VITTORIA OVEST E COMISO SUD
SUMMARY OF THE PROJECT
L¿INTERVENTO DI AMMODERNAMENTO, RELATIVO AD UNA VARIANTE ESTERNA AGLI ABITATI DI VITTORIA E COMISO, SI ESTENDE TRA IL KM 294+000 DELLA ATTUALE SS 115 E LA S.P. N.20 IN PROSSIMITà DI COMISO SUD, PER UNA LUNGHEZZA COMPLESSIVA DI CIRCA 10,7 KM, CON REALIZZAZIONE DI N 5 SVINCOLI (1¿VITTORIA OVEST, 2¿ VITTORIA NORD, 3¿VITTORIA EST, 4¿COMISO OVEST, 5¿COMISO SUD). LA SEZIONE STRADALE ADOTTATA Ê DI CATEGORIA C (EXTRAURBANA SECONDARIA), IN RIFERIMENTO AL D.M. 5/11/2001
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 10.70 km
- Achieved
- 0 km
Download project
Funding monitored
€ 164,000,000.00
of which cohesion funds
€ 163,650,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 163650000.00 |
Another public source | 350000.00 |
Payments monitored
€ 6,765,822.84
of which cohesion funds
€ 6,578,622.26
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 61685.59 | 61685.59 | 0 |
2020 | 629972.11 | 691657.70 | 0 |
2021 | 349814.11 | 1041471.81 | 0 |
2022 | 140033.14 | 1181504.95 | 0 |
2023 | 928682.83 | 2110187.78 | 1 |
2024 | 4655635.06 | 6765822.84 | 4 |
State of progress
Open
Expected start: 16/03/2025
Effective start: not available
Expected end: 17/09/2027
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale