CUP: J21B22000970001
¿REALIZZAZIONE DI COLLEGAMENTO DELL¿ASSE ATTREZZATO DI PESCARA E ADEGUAMENTO SVINCOLO S.S. 714¿. AMPLIAMENTO DI VIA A.DORIA ¿ SUB INTERVENTO 1
SUMMARY OF THE PROJECT
IL PRESENTE INTERVENTO PREVEDE LA RIQUALIFICAZIONE ED AMPLIAMENTO DELLA STRADA COMUNALE ¿VIA ANDREA DORIA¿ AL FINE DI COSTITUIRE L¿ASSE DI PENETRAZIONE, DALL¿ASSE ATTREZZATO ALL¿AREA PORTUALE, IL CONSEQUENZIALE ADEGUAMENTO DELLA VIABILITà CIRCOSTANTE E LA RIQUALIFICAZIONE DELLA BANCHINA SUD, AL FINE DI UN DECORO URBANO COMPLESSIVO DI TUTTA L¿AREA.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.75 km
- Achieved
- 0 km
Download project
Funding monitored
€ 6,123,000.00
of which cohesion funds
€ 6,123,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 6123000.00 |
Payments monitored
€ 1,837,560.30
of which cohesion funds
€ 1,837,560.30
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 90264.52 | 90264.52 | 1 |
2022 | 29708.01 | 119972.53 | 1 |
2023 | 1259877.11 | 1379849.64 | 22 |
2024 | 457710.66 | 1837560.30 | 30 |
State of progress
Open
Expected start: 01/05/2023
Effective start: 20/11/2023
Expected end: 20/08/2024
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- COMUNE DI PESCARA
- Beneficiary
- REGIONE ABRUZZO
At the School of OpenCohesion
OpenCoesione goes to School followed this project in edition 2023-24 with the team “DestinazioneDoria” of “ISTITUTO MAGISTRALE LICEO "G. MARCONI" PESCARA” of Pescara, PESCARA.
Read the Monithon report.
View the creative output.
Read the Monithon report.
View the creative output.
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale