CUP: C81B14000530006
REALIZZAZIONE DEL COLLEGAMENTO STRADALE DENOMINATO ¿CIRCONVALLAZIONE DI CAMPI BISENZIO: PROLUNGAMENTO DELLA CIRCONVALLAZIONE SUD DA VIA BARBERINESE ALLA NUOVA ROTATORIA DI CAPALLE¿.
SUMMARY OF THE PROJECT
REALIZZAZIONE DEL COLLEGAMENTO STRADALE DENOMINATO ¿CIRCONVALLAZIONE DI CAMPI BISENZIO: PROLUNGAMENTO DELLA CIRCONVALLAZIONE SUD DA VIA BARBERINESE ALLA NUOVA ROTATORIA DI CAPALLE¿.
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 2,378 km
- Achieved
- 0 km
Download project
Funding monitored
€ 5,314,000.00
of which cohesion funds
€ 5,314,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 5314000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 01/07/2021
Effective start: not available
Expected end: 31/10/2023
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- COMUNE DI CAMPI BISENZIO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale