CUP: F87H19000140006
CORRIDOIO STRADALE SALERNO - POTENZA - BARI CON ESTENSIONE DIRETTRICE BASENTANA: R.A. N. 05 E S.S. N. 407 - LAVORI DI RIQUALIFICAZIONE DELL'ITINERARIO 2° STRALCIO - 3° LOTTO - STRALCIO S - LAVORI PER IL RIPRISTINO STRUTTURALE DEGLI IMPALCATI ED IL RECUPERO FUNZIONALE DEI VIADOTTI COMPRESI TRA I KM 26+900 E 31+200 DELLA S.S. N. 407 "BASENTANA"
SUMMARY OF THE PROJECT
"L¿ITINERARIO BASENTANO, COMPRENDENTE IL RACCORDO AUTOSTRADALE N. 05 ¿SICIGNANO ¿ POTENZA¿ E LA STRADA STATALE N. 407 ¿BASENTANA¿, COSTITUISCE IL PRINCIPALE COLLEGAMENTO TRASVERSALE DELLA REGIONE TRA LA COSTA TIRRENICA E QUELLA IONICA, CONSENTENDO L¿INSERIMENTO DEL TRAFFICO REGIONALE NELLA GRANDE RETE STRADALE NAZIONALE. DETTO TRATTO AUTOSTRADALE Ê STATO REALIZZATO NEGLI ANNI 1960-1970, IN PARTE DA ANAS E IN PARTE DALLA EX CASSA DEL MEZZOGIORNO E COMPRENDE BEN N. 160 VIADOTTI E N. 35… read all
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 5 km
- Achieved
- 0 km
Download project
Funding monitored
€ 7,500,000.00
of which cohesion funds
€ 7,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 7500000.00 |
Payments monitored
€ 1,009,419.62
of which cohesion funds
€ 1,009,419.62
13%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2022 | 67215.97 | 67215.97 | 0 |
2023 | 0 | 67215.97 | 0 |
2024 | 942203.65 | 1009419.62 | 13 |
State of progress
Open
Expected start: 10/06/2024
Effective start: 10/06/2024
Expected end: 05/08/2026
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 7,500,000.00
- Payments on cohesion funds
- € 1,009,419.62
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale