CUP: F34E19000010001
SS 100"DI GIOIA DEL COLLE": SS 100- COMPLETAMENTO FUNZIONALE E MESSA IN SICUREZZA TRA I KM 44+500 E52+600 ( SAN BASILIO) CON SEZIONE DI TIPO B
SUMMARY OF THE PROJECT
L¿INTERVENTO SI PROPONE DI ADEGUARE L¿ATTUALE SEDE STRADALE DELLA S.S. 100 ALLA SEZIONE TIPO B DEL D.M. 5/11/2001, MEDIANTE LA REALIZZAZIONE DI UNA PIATTAFORMA STRADALE A DOPPIA CARREGGIATA, CON DUE CORSIE PER SENSO DI MARCIA E VIABILITà DI SERVIZIO DAL KM. 44+500 (IN CORRISPONDENZA DEL TERMINE DEL TRATTO GIà ADEGUATO) AL KM. 52+600 (LOCALITà SAN BASILIO).
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 8.10 km
- Achieved
- 0 km
Funding monitored
€ 84,000,000.00
of which cohesion funds
€ 84,000,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 84000000.00 |
- Other resources - To be found:
- € 39,261,748
Payments monitored
€ 284,785.47
of which cohesion funds
€ 284,785.47
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 114134.52 | 114134.52 | 0 |
2022 | 92873.10 | 207007.62 | 0 |
2023 | 77777.85 | 284785.47 | 0 |
State of progress
Open
Expected start: 01/04/2026
Effective start: not available
Expected end: 24/07/2029
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale