CUP: F91B17000710001
S.S.V. LICODIA EUBEA - LIBERTINIA: TRONCO SVINCOLO REGALSEMI - INNESTO SS 117 BIS: 2° STRALCIO FUNZIONALE - COMPLETAMENTO TRATTO B: DALLA FINE DELLA VARIANTE DI CALTAGIRONE (KM 12+470) AD INNESTO SS 117 BIS (KM 20+220)
SUMMARY OF THE PROJECT
L¿INTERVENTO, DI ESTESA PARI A CIRCA 9,0 KM, COSTITUISCE IL PROLUNGAMENTO DI UN PRIMO TRATTO GIà REALIZZATO ED IN ESERCIZIO, COMPRESO TRA LICODIA EUBEA E REGALSEMI, DI CUI PRESENTA LE MEDESIME CARATTERISTICHE FUNZIONALI. IL POTENZIAMENTO DEL COLLEGAMENTO CITATO VIENE OTTENUTO ATTRAVERSO LA REALIZZAZIONE DI UNA INFRASTRUTTURA (STRADA EXTRAURBANA SECONDARIA - CAT. C1 DEL DM 5/11/2001) DOTATA DI SVINCOLI A LIVELLI SFALSATI.
Implementation indicator
Lunghezza totale delle strade di nuova costruzione
- Target
- 9 km
- Achieved
- 0 km
Download project
Funding monitored
€ 230,000,000.00
of which cohesion funds
€ 227,500,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 230000000.00 |
Payments monitored
€ 12,854,690.73
of which cohesion funds
€ 12,357,610.60
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2018 | 105157.97 | 105157.97 | 0 |
2019 | 184726.40 | 289884.37 | 0 |
2020 | 831492.30 | 1121376.67 | 0 |
2021 | 502973.50 | 1624350.17 | 0 |
2022 | 1833774.00 | 3458124.17 | 1 |
2023 | 975973.39 | 4434097.56 | 1 |
2024 | 8420593.17 | 12854690.73 | 5 |
State of progress
Open
Expected start: 27/07/2023
Effective start: 27/07/2023
Expected end: 25/07/2027
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Beneficiary
- ANAS SOCIETA PER AZIONI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- PSC MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale