CUP: D98B20001110001
REALIZZAZIONE DI LAVORI AL CIMITERO COMUNALE (TERZO AMPLIAMENTO) VIA CIMITERO
SUMMARY OF THE PROJECT
REALIZZAZIONE DI LAVORI AL CIMITERO COMUNALE (TERZO AMPLIAMENTO) VIA CIMITERO
Implementation indicator
Progetti per la fruizione integrata e la promozione
- Target
- 32,047.50 num
- Achieved
- 32,047.50 num
Funding monitored
€ 27,911.10
of which cohesion funds
€ 27,911.10
Given name | Amount |
---|---|
Development and Cohesion Fund | 27911.10 |
- Economies:
- € 4,136.40
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Not started
Expected start: 11/01/2021
Effective start: 08/02/2020
Expected end: 28/02/2021
Effective end: 15/06/2021
Entities
- Planning body
- COMUNE DI VIBONATI
- Beneficiary
- COMUNE DI VIBONATI
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- INFRASTRUTTURE SOCIALI NEI COMUNI DEL SUD
- DCF strategic sector
- Infrastrutture
- DCF area axis
- Infrastrutture sociali